Monday, June 29, 2009

Sewer meeting set for Tuesday, 6/30

Williamson County officials will meet with Meadowgreen subdivision homeowners at 5:30 p.m. Tuesday in the County Administrative Complex for an update on the county sewer project.

County officials are providing sewer lines to residents living in the Meadowgreen, Hillsboro Acres, Brownwood and Farmington subdivisions in the Grassland area, where septic systems have begun to fail.

Late last year, Franklin leaders agreed to provide sewer treatment service for the project, even though the area is outside the city limits and its urban growth boundary.

The county complex is at 1320 W. Main St.

Sunday, June 28, 2009

December 6, 2010

http://www.williamsoncounty-tn.gov/index.aspx?NID=485

Meadowgreen/Grassland Sewer Construction Project

Meadowgreen/Grassland Area Sanitary Sewer Bid and Construction Anticipated Timeline Spring 2009

  • March 9, 2009 - Williamson County Commission approved for additional funding

  • April 19, 2009 - Advertise for Bids

  • May 1, 2009 - Receive Pre-Qualification packages from prospective contractors

  • May 19, 2009 - Open Bids Bids evaluated and selected bidder produces bonding and insurance for documents for contract documents, Contracts signed and Contractor ready to mobilize

  • June 15, 2009 - Notice to Proceed, 540 days for construction

  • December 6, 2010- Date of Completion