Meadowgreen/Grassland Sewer Construction Project
Meadowgreen/Grassland Area Sanitary Sewer Bid and Construction Anticipated Timeline Spring 2009
March 9, 2009 - Williamson County Commission approved for additional funding
April 19, 2009 - Advertise for Bids
May 1, 2009 - Receive Pre-Qualification packages from prospective contractors
May 19, 2009 - Open Bids Bids evaluated and selected bidder produces bonding and insurance for documents for contract documents, Contracts signed and Contractor ready to mobilize
June 15, 2009 - Notice to Proceed, 540 days for construction
December 6, 2010- Date of Completion